Field Name
|
R/O/C
|
Description
|
R
|
Date used for updating the statistics in the Damage/Cause Analysis report.
Example: 24.11.2000
|
|
R
|
Time used for updating the statistics in the Damage/Cause Analysis report.
Example: 10:50:05
|
|
O
|
Indicates that the status of the Service Request will also be set to "completed".
Example:
![]() |
|
O
|
Date when the malfunction started or the problem occurred.
Example: 18.11.2000
|
|
O
|
Time when the malfunction started or the problem occurred.
Example: 08:30:00
|
|
O
|
Date when the problem was solved or the malfunction ended.
Example: 24.11.2000
|
|
O
|
Time when the problem was solved or the malfunction ended.
Example: 09:45:00
|
|
O
|
Indicates that the piece of Equipment is no longer operating. This indicator triggers an update to the statistics in the Equipment Breakdown Analysis report.
Example:
![]() |
|
O
|
Duration of downtime for the piece of Equipment.
Example: 15
|
|
|
Unit of time for the quantity of breakdown duration, for example minutes or hours.
Example: H
|