Run MRP Single Item, Multi-level (MD02)
Purpose
Use this procedure to do an MRP run for an individual material at multiple levels. This is known as single-item, multi-level planning.
During single-item, multi-level planning, the material's Bill of Materials (BOM) is exploded and dependent requirements are created for assemblies and components. These components are also planned to cover dependent requirements. If the components have BOMs, they are also exploded and the system carries out the planning run for the components. The system repeats this process until all BOM levels have been planned.
Trigger
Perform this procedure when you must do an MRP run for an individual material at multiple levels.
Prerequisites
The following must exist:
•  Demand, e.g. planned independent requirements.
•  Material BOMs.
•  Material master data with MRP planning views created.
Navigation Path
Use the following navigation path to begin this transaction:
•  Select Processes è Manufacturing è MRP è Planning è Single Item Multi-level to go to the Single Item Multi-Level screen.
Helpful Hints
The following hints may assist you when running this type of MRP operation.
•  For daily MRP runs, NETCH (net change planning) provides the MRP Controller with all information about any MRP controlled material that has been impacted by recent demand. The MRP algorithms have been thoroughly optimised so that the run time and processor load is kept to a minimum.
Field Description Tables
The R/O/C column of each Field Description table indicates whether the field usage is:
R - Required in SAP.
O - Optional in SAP.
C - Conditional in SAP.
Procedure
1. Start the transaction using the navigation path.
screen  SAP Easy Access Main Menu
2. Double click on Single Item Multi-Level to go to the Single-Item, Multi-Level screen.
screen  Single-Item, Multi-Level
3. Complete the following fields:
Material
PIant
Processing key
Create pur req.
Schedule lines
Create MRP Iist
PIanning mode
Scheduling
 
Note NETCH (Net Change Planning) In net change planning, the system only plans materials that have undergone a change relevant to MRP since the last planning run NETPL (Net change planning in the planning horizon) You can also use a planning horizon to further limit the scope of the planning run. In "net change planning in the planning horizon", the system only plans materials that have undergone a change that is relevant to the planning run within the period which you defined as the planning horizon. Regenerative planning (NEUPL) The system plans all the materials that are contained in the planning file. While this appears to be an option, it can only be used in background planning, not single item planning.
4. Click Image checkbox to insert a tick if you want to display the material list.
Note If you set the indicator, then all components contained in the BOM are planned and the system places the planning results in the main memory without initially saving them to the database.
Note The planning results are displayed automatically in the material overview. Exception messages warn you about problems at a lower BOM level. You can change the planning results to solve any problems. The system does not save the planning results until you chooseSave.
5. Click Image checkbox to insert a tick if you want to simulate the MRP run.
Note You may select Settings è Save to save the parameters you have entered.
screen  Single-Item, Multi-Level
6. Click Image to skip the system messages and go to the Planning report screen.
screen  Planning report
Note You may scroll down the screen to see more information.
7. Click Image to go to the Planning Result: Overview screen.
screen  Planning Result: Overview
Note The checkbox Checkbox Selected to the right of the material description shows that new exception messages have been created.
8. Click Image to see a complete list of the possible exception messages.
screen  Selection group (1) 41 Entries found
9. Click Image to close the exception message window and return to the Planning Result: Overview screen.
10. Click Image next to a material.
11. Click Image to go to the Planning Result: Individual Lines screen.
screen  Planning Result: Individual Lines
Note You may click Image or Image to go to the previous, or next selected materials.
12. Perform one of the following, if required:
If
Then
You want to determine pegged requirements
ClickImage.
You want define the goods receipt date
Click Image .
You want define the availability data
Click Image .
You want review vendor details
Click Image .
You want review customer details
ClickImage.
You want return to the Planning Result: Individual Lines screen
Click Image .
 
13. Click Image to change the plan details.
screen  Planning Result: Individual Lines
14. Click Image to create a new order proposal.
screen  Select Order Proposal
15. Enter the required Planned order profile or Purch.reqisition key in the respective field.
16. Perform one of the following:
If
Then
Go To
You want to define a planned order
Double click Radio Button Selected Planned order.
You want to define a purchase requisition
Double click Radio Button Selected Purchase requisition.
You want to insert a manual firming date
Double click Radio Button Selected Delivery schedule.
You do not want to do any of the above
---
 
screen  Process Order Proposal
17. For example, complete the following fields:
Order qty.
OrderStart
 
18. Click Go Back to return to the Planning Result: Individual Lines screen.
19. Return to Step 16.
screen  Process Order Proposal
20. For example, complete the following fields:
Purchase Requisition
Purch.org.
 
21. Click Go Back to return to the Planning Result: Individual Lines screen.
22. Return to Step 16.
screen  Planning Result: Individual Lines
23. Click Image if you want to insert a manual firming date.
screen  Enter Manual Firming Date
24. For example, complete the following field:
Firm date
 
25. Click Image to close the pop-up window.
screen  Planning Result: Individual Lines
Note The system displays the message, "Manual firming date xx.xx.xxxx set."
26. Perform one of the following, if required:
If
Then
Go To
You want to compare the results with the Stock / Requirements list
Select Goto è Comparisonè Stock/requirements list
You want to compare the results with the MRP list
Select Goto è Comparisonè MRP list
You do not want to do any of the above.
---
 
screen  Comparison of Operative Planning and Stock/Requirements List
27. Review the information as required.
28. Perform one of the following:
If
Then
You want to review a period
Click on the period then click Image .
You want to review current plans
Click Image .
You want to review the list
Click Image .
 
29. Click Go Back to return to the Planning Result: Individual Lines screen.
30. Return to Step 26.
screen  Comparison of Operative Planning and MRP list
31. Review the information as required.
32. Perform one of the following:
If
Then
You want to review a period
Click on the period and then click Image .
You want to review current plans
Click Image .
You want to review the list
Click Image .
 
33. Click Go Back to return to the Planning Result: Individual Lines screen.
34. Return to Step 26.
screen  Planning Result: Individual Lines
35. Click Image to save your planning results and go to the Planning Result: Overview screen.
screen  Planning Result: Overview
Note The Image symbol indicates that there are problems with planning requirements and the supply of material CSB-297 that is of the highest priority according to the traffic light set up.
Note The Image symbol indicates that these materials currently meet the planned requirements for manufacture.
36. Click Image to return to the SAP Easy Access Main Menu screen.
37. You have completed this transaction.
Result
You have successfully run MRP at Single Item, Multi-level. Typically, the next step in the production process is to convert the planned orders.
Reference Refer to the procedure Collective Conversion of Planned Orders.